Egyptian Lacquer Manufacturing Company Cleanup

 

Egyptian Lacquer Manufacturing Company (ELMCO) is a paint and lacquer manufacturing facility that is located at 113 Fort Granger Drive, Franklin, Williamson County, Tennessee. In January, 2007, sampling along Liberty Creek, near the facility, was conducted by the City of Franklin and TDEC in response to complaints from citizens of strong odors from the creek. Analytical results from the samples confirmed the presence of toluene and acetone in both water and air samples. The Department initiated emergency response actions to contain the chemicals using its emergency response contractors. Upon further investigation by TDEC, the acetone and toluene were found to be entering Liberty Creek and the Harpeth River through seeps along the banks of the creek and river.

 

At TDEC’s request, ELMCO conducted an immediate investigation of their above ground solvent storage tank farm and the associated underground pipelines that carried various solvents to the manufacturing facility. On February 28, 2007, the investigation revealed that the toluene and acetone pipelines had been compromised and leaked solvents into the subsurface. ELMCO agreed to assume responsibility for continuing the response efforts at the seeps along Liberty Creek and the Harpeth River, and to initiate further efforts to delineate the extent of contamination in soil and groundwater resulting from the solvent release. The following is a brief summary of the activities that ELMCO has undertaken to address the contamination caused by the facility:

 

» Placement of booms and pads along the seeps in Liberty Creek and the Harpeth River to collect any free product.

 

» Installation of an interceptor trench, measuring 140‘ by 15‘, along Liberty Creek to intercept the free product before it reaches the creek.

 

» Air monitoring to insure that vapors do not pose a risk.

 

» Installation of monitoring wells to delineate contamination and monitor contaminant concentrations.

 

» Monthly sampling of seeps along Liberty Creek and the Harpeth River.

 

» Delineation and bioremediation of contaminated soils on site.

 

» Permanently decommissioned pipeline that transported solvents to the facility.

 

» Permanent removal of all above ground storage tanks to be completed by April, 2008.

 

In accordance with the requirements of a Voluntary Consent Order, entered into between TDEC and Egyptian Lacquer on June 1, 2007, a Corrective Action Plan (CAP) was submitted to TDEC on August 28, 2007. TDEC found the CAP to be deficient, and an amended CAP will be submitted by ELMCO to TDEC by April 4, 2008.

 

TDEC has established links on its website in an effort to facilitate public access to specific documents submitted by ELMCO. These documents will include analytical results from soil, air, and water sampling events, as well as any workplans that require TDEC approval. As documents come into the Department, they will be posted in a timely manner for public review.

 

 

Correspondence

» TDEC's Determination That Interim Measures Have Been Completed By Elmco - March 24, 2010

 

» ELMCO Interim Measures Update And Request For TDEC's Determination of Completeness - October 30, 2009

 

 

Public Notice

» The Egyptian Manufacturing Company - Public Meeting Concerning Revised Corrective Action Plan August 7, 2008.

 

» Public Meeting - Response to Comments

 

 

Reports

» ELMCO March 2013 Seep and Surface Water Report

 

» ELMCO March 2013 Groundwater Monitoring Report

 

» ELMCO December 2012 Seep Sampling Report

 

» ELMCO December 2012 Groundwater Monitoring Report

 

» ELMCO September 2012 Groundwater Monitoring Report

 

» ELMCO October 2012 Seep Sampling Report

 

» ELMCO July 2012 Seep & Surface Water Sampling Report

 

» ELMCO June 2012 Groundwater Monitoring Report

 

» ELMCO December 2011 Groundwater Monitoring Report

 

» ELMCO December 2011 Seep Sampling Report

 

» ELMCO September 2011 Groundwater Monitoring Report

 

» ELMCO June 2011 Seep and Surface Water Monitoring Report

 

» ELMCO June 2011 Groundwater Monitoring Report

 

» ELMCO December 2010 Seep and Surface Water Sampling Report

 

» ELMCO December 2010 Groundwater Monitoring Report

 

» ELMCO July & October 2010 Seep and Surface Water Sampling Report

 

» Final ATSDR Certified Health Consultation - Residential Indoor Air Investigation, Egyptian Lacquer Manufacturing Company, November 22, 2010

 

» ELMCO June 2010 Groundwater Monitoring Report

 

» ELMCO June 2010 Seep And Surface Water Sampling Report

 

» ELMCO April 2010 Seep and Surface Water Sampling Report

 

» ELMCO February 2010 Seep and Surface Water Sampling Report

 

» ELMCO December 2009 Seep and Surface Water Sampling Report

 

» ELMCO December 2009 Groundwater Monitoring Report

 

» ELMCO September 2009 Groundwater Monitoring Report

 

» ELMCO October 2009 Seep and Surface Water Sampling Report

 

» Historical Summary Chart for Water Quality Sample Results: Jan. 2007 - Aug. 2009

 

» Historical Summary Graph for Water Quality Sample Results: Jan. 2007 - Aug. 2009

 

» State Lab Water Quality Sample Results for August 3

 

» July 27, 2009 Report of Bedrock Surface Data – Daniels Drive Area

 

» ELMCO June 2009 Groundwater Monitoring Report

 

» ELMCO June 2009 Seep & Surface Water Sampling Report

 

» Final Report For Vapor Intrusion - Daniels Drive Area, Franklin, Tennessee

 

» ELMCO April 2009 Seep Sampling Report

 

» ELMCO March 2009 Groundwater Monitoring Report

 

» WPC's March 2009 Water Sampling Report

 

» Map of sample locations for WPC 3-23-09 sampling event

 

» WPC's March 2009 Summary of Water Sampling Results

 

» ELMCO February 2009 Seep Sampling Report

 

» ELMCO December 2008 Groundwater Monitoring Report

 

» ELMCO December 2008 Seep Sampling Report

 

» ELMCO November 2008 Seep Sampling Report

 

» WPC's October 2008 Summary of Water Sampling Results

 

» ELMCO October 2008 Seep Sampling Report

 

» ELMCO September 2008 Seep Sampling Results

 

» ELMCO September 2008 Groundwater Monitoring and Investigation Report

 

» WPC's September 2008 Summary of Water Sampling Results

 

» WPC's September 2008 Water Sampling Report

 

» ELMCO Seep Sampling Report September, 2008 (replaces August 2008 sampling)

 

» TDEC TRIP Report - August 12, 2008

 

» ELMCO July 2008 Seep Sampling Report

 

» ELMCO June 2008 Seep Sampling Report

 

» WPC's June 2008 Summary of Water Sampling Results

 

» WPC's June 2008 Water Sampling Report

 

» ELMCO's June, 2008 Groundwater Monitoring Results

 

» Initial Report of Confirmation Soil Sampling Investigations Under Former Tank Farm and in Biox Treatment Area at ELMCO Facility

 

» ELMCO Seep Sampling Results May 2008

 

» Seep Monitoring Results - April 2008 Event

 

» ELMCO Investigation Report - March 25, 2008

 

» WPC's Summary of Water Sampling Results from Liberty Creek

 

» Water Sampling Results from Liberty Creek - March 18, 2008

 

» ELMCO Seep Sampling Report - February, 2008

 

» ELMCO Seep Sampling Report - January 28, 2008

 

» WPC's Summary of 2007 Water Sampling Results from the Harpeth River and Liberty Creek

 

» ELMCO Seep Sampling Report - December 10, 2007

 

» ELMCO Seep Sampling Report - November 9, 2007

 

 

Plans

» Revised Comprehensive Corrective Action Plan Addressing The Solvent Release From ELMCO, June 23, 2008

 

» Attachment A of the ELMCO Revised Comprehensive Corrective Action Plan

 

» ELMCO Investigative Workplan - December 20, 2007

 

» ELMCO Air Monitoring Plan - December 14, 2007

 

 

Biostimulation Conducted At ELMCO By Aquaeter

» Project Status - March 18, 2013 Update

 

» Project Status -January 2, 2013 Update

 

» Project Status - August 2012 Update

 

» Project Status - May 2012 Update

 

» Project Status - January 2012 Update

 

» Project Status - End of August 2011 Update

 

» Project Status - End of May 2011 Addendum

 

» Project Status - End of May 2011 Update

 

» Project Status - End of March 2011 Update

 

» Project Status - End of January 2011 Update

 

» Project Status - Monitoring